Oregon O logo University of Oregon > Campus Planning & Real Estate Main Page > Projects > Completed Projects
CAMPUS PLANNING AND REAL ESTATE

 

Completed Between 1997 and 2008    
  • (listed in alphabetical order)
  •  

    ALLEN HALL RENOVATION

    Rapid growth of the student body and faculty in the School of Journalism and Communication, along with escalating needs for specialized classrooms and resource facilities, has triggered the need to renovate Allen Hall. Planning for the complete renovation of Allen Hall was based on a November 13, 1995 master plan study by Boucher Mouchka Larson Architects (BML). Phases I and II were completed
    in earlier years. Total project budget: $3.5 million.

     


    ALLEN HALL RENOVATION PHASE III - RESOURCE ROOM

    Interior Photo, Exterior Photo

    Size: approximately 1,400 sf remodeling (1 floor)
    Total Project Budget: approximately $373,000 private funds (Direct construction $283,053) (Project cost $372,965)
    Architect: Boucher Mouchka Larson Architects (BML), Portland
    Construction Firm: Morris P. Kielty, Eugene
    Project Manager: Alex Gordon
    Project Planner: Chris Ramey

    This phase created a Resource Room (Willis S. Dunaway Journalism Resource Room), which provides new space designed for study, meetings, and student research. As the School's curriculum increasingly becomes project-oriented with strong emphasis on team and individual projects, space is needed for student meetings and team conferences, and students need greater access to computers and computer networks. The Resource Room meets all of these needs. In addition, a schematic design for a new entry was completed. Construction was completed in Spring 1999.


    ALLEN HALL RENOVATION PHASE IV

    Exterior Photo 1, Interior Photo

    Size: approximately 1,100 SF addition (1 & 2 floors)
    Total Project Budget: approximately $850,000 private funds (Direct construction $726,565) (Project cost $850,112)
    Architect: Boucher Mouchka Larson Architects (BML), Portland
    Landscape Architect: Cameron McCarthy Gilbert, Eugene
    Construction Firm: Morris P. Kielty, Eugene
    Project Planner: Chris Ramey
    Project Manager: Alex Gordon

    This phase included the creation of a new 1,100 SF building entry which efficiently connects the two portions of the lower floors with each other and with the rest of the building. Additionally, because the ground floor of the building is below grade, an entry plaza was designed to adjust from the surrounding grade to the entrance level through a series of gradual transitions to the existing contours.

    Phase IV included a conference room devoted to alumni recognition and the Dean's Complex, consisting of a two-room Dean's suite with private office, staff office and support area. Construction began in Summer 1999 and was completed in April 2000.


    ALLEN HALL RENOVATION, Phase V

    Size: approximately 21,700 gsf remodeled space
    Total Project Budget: approximately $2,000,000 in mostly gifts, but also including $561,800 in G-bonds. (Direct construction $633,000) (Project cost $1,060,000)
    Architect: Boucher Mouchka Larson Architects (BML), Portland, OR, (503) 223-4886
    Construction Firm: DPR Construction, Eugene, OR, (541) 341-1329
    Project Planner: Chris Ramey, (541) 346-5562
    Project Manager: Alex Gordon, (541) 346-5219

    Description: This phase made improvements to the second and third floors including conversion of the resource room to an electronic classroom and conversion of the old Dean's office to faculty offices.

    Status: Construction completed Fall 2001.


    (SCHOOL OF) ARCHITECTURE AND ALLIED ARTS ADDITIONS AND ALTERATIONS

    Location: Lawrence Hall
    Size: 52,000 sf (5 story)
    Total Project Budget: Lawrence Hall: (Direct construction $4,953,479) (Project cost $6,221,654)
    Millrace 3: (Direct construction $1,072,578) (Project cost $1,503,826)
    North Site East: (Direct construction $907,356) (Project cost $926,703)
    Total Project Cost: $8.65 million
    Architect: BOORA Architects, Portland
    Contractor: (Lawrence Hall) John Hyland Construction, (Millrace 3) 2G Construction Company, (North Site East) Lee Construction Company

    Description: This project constructed an approximately 52,000 sf, five-story addition to Lawrence Hall, including an expanded AAA library, classrooms, offices, and art gallery. The design included a new southern facade which created a welcoming entry to the building. On the north site (north of Franklin), a new woodshop, and architecture studios (Millrace 3) were constructed, and the fine arts painting and photographic studios were renovated. Project was completed in 1991.


    AUTZEN STADIUM

    Location: Autzen Stadium
    Size: approximately 12,000 new seats and renovation.
    Total Project Budget: $89.7 million (February 2000 emergency board $19.7 million F-bonds, $60.3 million gifts, November 2001 emergency board $9.7 million F-bonds) (Direct constructin $81,126,901) (project cost $89 million)
    Architect: Ellerbe Becket, Kansas City, MO (816) 561-4443
    Construction Firm: Hunt/Wildish, Eugene (541) 485-1700
    Project Planner: Chris Ramey, (541) 346-5562
    Project Manager: Charlene Lindsay, (541) 346-5276

    Description: The stadium expansion design addressed the need to expand seating capacity and the need to improve circulation, accessibility, restrooms, concessions, and press facilities. It took into consideration the original design by Skidmore, Owings, and Merrill, which displays axial geometry, symmetrical massing, easily understood circulation, and the use of the berm as a podium for the stadium. The phased expansion and renovation project added 12,000 new seats, 3,000 of which are located in a new covered "club section," along with 32 new skyboxes, a three-story luxury suite, and improved concession stands. These improvements are expected to produce more revenue, thus helping the athletic department to become completely self-funding. The total stadium capacity increased from 41,700 to 53,800 seats.

    The site master plan addressed the need for improved circulation, parking, transit capacity, accessibility, and pre-game activity amenities (including new restroom facilities).

    The schematic design was completed in winter 2000. Phase 1 of the project, including landscaping of the north berm, was completed in 2000. Phase 2, including new artificial turf; the new bus transit station; new water, sewer, and electrical facilities; new ticket booths; and a decorative fence around the stadium, was completed in summer 2001. Phase 3, including the addition of 12,000 new seats, improved restrooms, concessions, and walkways, were completed before the 2002 football season. Phase 4, including the addition of new sky suites and pressbox, was finished by the 2003 season.

    Status: Completed summer 2003.


    BOWERMAN FAMILY BUILDING

    Location: Hayward Field
    Size: 17,500 gsf
    Total Project Budget:
    Architect: Stafford Architects

    Description: This gifted building was constructed on university land at the north end of Hayward Field/Stevenson Track and donated to the UO by the Bill Bowerman family. The Bowerman Family Building spreads is east and south wings around the northwest corner of Stevenson Track at Hayward Field. On meet days it marks the major entrance to the facility from the center of camus. The 17,500 gsf building houses the International Institute for Sport and Human Performance; it also contains track-team offices and locker rooms, a meeting room, a circuit-training room, and a treatment facility staffed by athletic trainers. Project was completed in 1992.


    CAMPUS DEVELOPMENT PROJECT

    Faced with the twin challenges of increased numbers of students and outmoded classroom facilities, the university embarked on a three-phase project to expand and modernize core academic space on the campus. Stage One (see
    William W. Knight Law School) of the project relocated the Law School to a new building on land available at the eastern edge of the campus periphery (completed), freeing up the central campus space of the previous Law building (McKenzie Hall) for general educational uses. The renovation of McKenzie Hall, Stage Two (see McKenzie Hall Renovation), is also completed. Stage three of the project is the Lillis Hall/Gilbert Hall Additions and Alterations Project. Lilles Hall was completed in winter 2004


    CAMPUS DIAGNOSIS STUDIES

    Project Planner: Christine Thompson, (541) 346-5572

    The purpose of diagnosis studies is to record the existing conditions of the campus as they relate to the university's Long Range Campus Development Plan's policies and patterns. These studies aid in decision making for potential development of the area, as well as help identify the need for future amendments to the Long Range Campus Development Plan.

    For more information click here.

    Status: Completed.


    CAMPUS OUTDOOR LIGHTING PLAN

    Project Planner: Christine Thompson, (541) 346-5572

    Description: The purpose of the Campus Outdoor Lighting Plan is to interpret and enhance the existing Long Range Campus Development Plan (LRCDP) outdoor lighting policies creating a Level 3 Plan. The plan defines lighting parameters for entrances, pedestrian walkways, and parking lots on campus. It also describes review requirements and defines the campus standard light fixture design.

    Outdoor lighting on campus has received a great deal of attention over the years. This plan is designed to address the key issues and concerns surrounding the subject. Establishing a plan (in particular prioritizing outdoor lighting walkways) will also allow the CPC to review outdoor lighting improvements in a comprehensive manner, thus eliminating the need for individual lamp location reviews.

    Status: Completed winter 2004.

     


    CAMPUS PLAN UPDATE

    Project Planners: Chris Ramey, (541) 346-5562 and Christine Thompson, (541) 346-5572

    The University of Oregon began the process of updating its Campus Plan (previously known as the 1991 Long Range Campus Development Plan) in the summer of 2004.

    The Campus Plan describes the guiding principles (or patterns) and policies that define the type and extent of future campus development. The 1991 LRCDP was written nearly fifteen years ago. It has effectively guided the university through an active period of development and improvements resulting in a noticeably enhanced campus environment. Change happens incrementally, making an overall guiding plan essential. The plan's basic precepts remain very effective. Nonetheless, it is important to revisit portions of the LRCDP to evaluate potential improvements to the planning process and to fix outdated information. These efforts will ensure that the LRCDP will serve the campus for the next ten years.

    A draft updated Campus Plan was completed and reviewed by a wide body of individuals and groups during a three-month time period beginning January 11, 2005 and ending with the CPC April 12, 2005 public hearing. The Campus Planning Committee reviewed the comments and suggestions gathered during this review period prior and took action May 24, 2005. The CPC's recommendation for approval was supported by university administration.

    Click here to see the updated Campus Plan.

    Status: Completed


    CAMPUS TREE PLAN

    Project Planner: Christine Thompson, (541) 346-5572

    The Campus Tree Plan, created by the Campus Planning Committee, guides the future care for the trees on campus ensuring that they remain a vital component of the campus environment. The university has had in place other policies (Long Range Campus Development Plan) which address tree management, but the policies lacked specificity and were not comprehensive. The new Campus Tree Plan ensures that all development, repair, maintenance and operations of the University of Oregon campus incorporate tree management principles addressing tree protection, tree replacement, landscape design, and environmental sustainability.

    The Campus Tree Plan was completed in October, 2001.


    (LEN) CASANOVA CENTER

    Location: Autzen Stadium
    Size: 99,000 sf
    Total Project Budget: 1989 legislature SB 5572 $7,095,000 gifts (Direct construction $9,451,183) (Project cost $11,658,650)
    Architect: The Amundson Associates, Springfield
    Contractor: John Hyland Construction (and phase IIB by Elliott-Jochimsen Construction)

    Description: This $11.7 million project constructed a 99,000 square foot building to house various athletic department services, including administration and offices for team coaches and their staffs. The facility contains state-of-the-art weight-training and fitness rooms; training rooms, medical treatment facilities, whirlpool baths, showers, team and coaching locker rooms, and multi-purpose areas such as meeting rooms and a retail store. The upstairs central lobby features the University of Oregon Hall of Champions, which honors the greatest athletes, coaches and teams of Oregon's athletic history. The project was dedicated on September 27, 1991.


    COMPUTING CENTER REMODEL

    Location:
    Size: approximately 10,000 gsf
    Total Project Budget: (Direct construction $341,148) (Project cost $471,292)
    Architect: Robertson/Sherwood Architects, Eugene, (541) 342-8077
    Contractor: Preferred Construction, Springfield

    Description: This remodeling effort of the Computing Center was long overdue. When the Computing Center was built in 1966, computing was oriented toward large machines and punch-card data, and little thought was given to the staff associated with those functions. Staff had long outgrown this space as well as the second floor addition that was added in 1970. Once Microcomputer Customer Services was moved to McKenzie Hall in 2000, focus shifted to improving the Computing Center. The remodel of both floors, approximately 10,000 gsf, improved the remaining Computing Center operations. Construction was completed in fall 2001.


    EAST CAMPUS (MOSS STREET) CHILDREN'S CENTER

    Location: East Campus
    Size: 13,500 sf
    Total Project Budget: 2001 legislature SB 5525 $2.616 million F-bonds (Direct construction $2.3 million) (Project cost $3.2 million)
    Architect: Mahlum Architects, Portland, OR, (503) 224-4032
    Construction Firm: Ordell, Springfield, OR, (541) 747-8734
    Project Planner: Dorene Steggell, (541) 346-5606 Project Manager: George Bleekman, (541) 346-2625

    This 2.8 million dollar 13,500-square-foot project replaced the former Child Care and Development Center facilities occupying houses in East Campus and the EMU. The new Center serves approximately 120 children, infants through school-aged, of university students, faculty, and staff. The Center has many sustainable aspects, including daylighting, and ground-source heat pumps.

    Status: The grand opening was held in May 2004.


    EAST CAMPUS DEVELOPMENT POLICY UPDATE

    Project Planners: Chris Ramey, (541) 346-5562 and Christine Thompson, (541) 346-5572

    The university, with input from neighbors and campus community members, created a new policy for East Campus development. The policy's goal is to provide for the expansion of the institution, based on its needs, without diminishing the quality of the surrounding neighborhood. It describes the type and extent of future development in the East Campus Area. The policy addresses the following key elements: university mission, graceful edges, campus-like character, traffic, parking, maintenance, and communication.

    Click here for more information about the project.

    Status: The project was completed Fall 2004.



    EAST CAMPUS FRAMEWORK STUDY

    For more information, contact the University Planning Office:

    Chris Ramey - Director and Architect (541) 346-5562
    Christine Thompson - Planning Associate (541) 346-5572


    EAST CAMPUS GRADUATE VILLAGE

    Location: near Bean Complex
    Size: 41,600 gsf (2 buildings 20,800 gsf each)
    Total Project Budget: June 2000 Emergency Board; $4.1 million F-bonds from Auxiliaries (Housing). (Direct construction $3,126,507) (Project cost $3,889,190)
    Architect: gLAs Architects, Eugene
    Contractor: Essex General Construction, Inc., Eugene

    Description: This 70-unit residence hall for graduate students is sited on 1.4 acres near the existing Bean Complex on the eastern edge of the campus. The residence hall is comprised of two wood-framed structures, each 20,800 gross square feet, built around a shared open space. The studio and one-bedroom apartment-style units are designed for single occupancy, each including a private bath and kitchen facilities. Construction was completed in 2001.


    EASTGATE

    Sketches: Goal 1, Goal 2, Goal 3, Goal 4

    Landscape Architect: Cameron McCarthy Gilbert & Scheibe, Eugene, along with the consulting firm of Moore, Iacofano, and Goltsman (MIG), Eugene.
    Project Planner: Dorene Steggell

    This project is one of a series of projects that looks at ways to improve campus gateways. Well-developed entrances to the campus increase coherency and create a sense of the campus as a definable space. The Eastgate project covers the area between Oregon Hall and the University Health and Counseling Center and its surroundings. This area is particularly important because it is the first point of arrival for prospective students, staff, faculty, and campus visitors. It also is a key component of the university's vehicular circulation system.

    A steering committee was established and worked with the landscape architecture firm on the Feasibility Study. A workshop was held February 5, 1999 to gain input from a broader focus group. The results of this meeting were presented at a campus-wide presentation.

    The Feasibility Study report, completed August 1999, identified four conceptual goals: (1) sense of arrival, (2) traffic control, (3) reflection of the Oregon landscape, and (4) front doors to buildings.


    (COLLEGE OF) EDUCATION ADDITIONS AND ALTERATIONS

    Size: approximately 94,000 gsf new construction and 17,000 gsf alterations
    Total Project Budget: approximately $40 million
    Architect: Zimmer Gunsul Frasca Partnership, Portland, OR, (503) 224-3860
    Project Planner: Chris Ramey, (541) 346-5562
    Project Manager:

    The College of Education is growing in response to a statewide need for effective teachers and school administrators and for substantial growth in research and service funding. The investment in physical facilities is essential to sustaining faculty productivity, program quality and impact of faculty research and outreach services. Faculty, staff and students have been assigned to crowded, substandard and/or remote structures. The recommended addition of 94,174 gsf of new space and renovation of 17,200 gsf of existing space will remedy current, serious space and functional problems and provide a modest increment for growth, if used prudently.

    Status: The project is anticipated to begin construction in winter 2008 with completion in fall 2010.


    EMU MASTER PLAN

    Size: approximately 213,000 gsf (three floors)
    Total Project Budget: approximately $200,000
    Architect: MHTN Architects, Salt Lake City, UT, (801) 595-6700
    Project Planner: Chris Ramey, (541) 346-5562

    Since 1950, the Erb Memorial Union (EMU) has been the gathering place for campus activities at the University of Oregon. It houses more than 150 student groups and provides lounges, art galleries, a variety of food venues, a pool hall and arcade, a number of services, group meeting rooms, and a staff of program consultants to assist the student groups. The fifty-year-old building has undergone at least three additions or renovations during its lifetime.

    This master plan contains a conceptual program for accommodating the EMU's space needs for the next 20 years, and a basic diagrammatic vision for how the needed space can be accommodated including identification of discrete construction phases which could be implemented over a number of years.

    Status: The master plan is completed.


    ERB MEMORIAL UNION FOOD SERVICE & REC CENTER IMPROVEMENTS

    The Fish Bowl Photo, The Buzz Photo, Rec Center Photo

    Size: approximately 3,000 addition; 49,000 SF remodeled/renovated; (2 floors)
    Total Project Budget: 1995 legislature SB 5555, $4,150,000 Student buildings fees (Direct construction $3,224,000) (Project cost $4.5 million)
    Architect: McBride/Seder Architects, Portland
    Construction Firm: Wildish Building Co., Eugene
    Project Planner: Fred Tepfer
    Project Manager: Garry Fritz

    This project remodeled the south and west areas of the basement and ground floors of the Erb Memorial Union building. Completed in the summer of 1998, it revised and improved circulation and visibility in the Fishbowl and south dining room areas, restoring many circulation patterns that were disrupted by the previous building addition and remodel. At the basement level, the project added approximately 3,000 square feet, revising and clarifying the corridors and circulation, and remodeling the Recreation Center and Quick Copy. The Convenience Store is also now located in the remodeled space. The new north addition, next to the current breezeway and with an entrance clearly visible from 13th and University, contains a coffee house. Source of funds: 85% building fees; 15% state system utilities funds.


    ERB MEMORIAL UNION AMPHITHEATER

    Photo

    Size: courtyard
    Total Project Budget: approximately $415,000 from incidental fees (Direct construction $351,000) (Project cost $415K)
    Landscape Architect: Cameron McCarthy Gilbert, Eugene
    Construction Firm: Wildish Construction Co., Eugene
    Project Planner: Fred Tepfer
    Project Manager: Garry Fritz

    This project, completed in the summer of 1998, was initiated on behalf of the ASUO by the 1996-97 ASUO President to commemorate the organization's 100-year anniversary. The project repaired and improved the portion of the campus located between the EMU and the intersection of 13th Avenue and University Street (approximately 24,000 SF). The landscape architect worked with a user group of students, faculty, and staff. The project removed paving and some of the existing trees and constructed a plaza near the intersection, one more suitable for large group gatherings than the previous series of smaller spaces. It includes a raised "stage," and all areas are accessible by gently sloping sidewalks that are more manageable for people with disabilities. The project creates a more open view of the EMU and also includes a clear path up to the main entrance of the building. This project's support was due largely to enormous efforts on the part of the ASUO, the user group, the consultant, and the general contractor working in very complementary and productive ways. Source of funds: student incidental fees.


    ERB MEMORIAL UNION ELEVATOR

    Photo

    Size: elevator addition (1 floor)
    Total Project Budget: approximately $555,000 - Student building fee financing (Direct construction $351,000)
    Architect: Robertson/Sherwood Architects, Eugene
    Construction Firm: 2G Construction
    Project Planner: Chris Ramey
    Project Manager: Alex Gordon

    This project, comprised of an elevator in the Erb Memorial Union building, provides access to the International Student Lounge, the Oregon Daily Emerald offices, and the Adell McMillan Art Gallery. Construction was completed in Winter 2000.

     


    ERB MEMORIAL UNION OUTDOOR PROGRAM TRIP FACILITY

    Size: 4,000 sf
    Total Project Budget: 1989 legislature SB 5572, $325,000 Auxiliaries (Direct construction $247,010) (Project cost $328,751)
    Architect: WEGroup Architects, Eugene
    Contractor: Morris P. Keilty, General Contractor

    Description: The Outdoor Program uses this 4,000 square foot, single-story building at the corner of 18th Avenue and University Street for trip preparation and storage of recreational equipment. Project completed in 1992.


    fMRI FACILITY/STRAUB HALL ADDITIONS AND ALTERATIONS

    Size: approximately 1,000 gsf addition and 2,000 gsf remodel (one story)
    Total Project Budget: $4,495,400 (1999 Legislature SB 5021 $1,166,000 G-bonds, $1,166,000 gifts; November 2000 emergency board $1,584,000 grants, $579,000 other) (Direct construction $1,198,900) (Project cost $1,576,911)
    Architect: L. A. Kersh Architecture, Eugene, (541) 334-6408
    Construction Firm: Hyland Construction, Springfield, OR, (541) 725-8081
    Project Planner: Dorene Steggell, (541) 346-5606
    Project Manager: George Bleekman, (541) 346-2625

    Description: The Straub Hall Additions and Alterations Project, completed in spring 2002, provides additional space for the Psychology Department. The project included a small addition which houses the new fMRI facility, plus a remodel of adjacent existing space on the first floor of Straub Hall. The new Lewis Neuroimaging Center permits imaging of brain function and brain tissue that will allow scientists to better correlate the brain's anatomy with human thought and behavior.

     


    HEART OF CAMPUS

    Total Project Budget: 2003 legislature HB 5028, approximately $850,000 gifts (Direct construction $339,744) (Project cost $603,891)
    Landscape Architect: Cameron McCarthy Gilbert Scheibe, (541) 485-7385
    Construction Firm: Wildish Companies, (541) 485-1700/UO Landscape Students
    Contractor: Gale Roberts Co., Eugene
    Project Planner: Dorene Steggell, (541) 346-5606
    Project Manager: Janet Lobue, (541) 346-5259

    Construction is complete on the new Heart of Campus, which consists of replacement of the existing kiosk and the creation of a pedestrian-friendly plaza at the intersection of 13th Avenue and University Street. The project was funded by the sale of engraved bricks to commemorate the 125th anniversary of the University, and by the Department of Public Safety. The School of Architecture and Allied Arts and Facilities Services made significant in- kind contributions. The kiosk and surrounding areas were designed and constructed by UO Landscape students working with Professor Stan Jones. The street improvements were designed by Cameron McCarthy Gilbert Schiebe.

    Status: Completed in fall 2004.


    (LEE) KELLY SCULPTURE

    Total Project Budget: approximately $25,000
    Engineering Consultant: MR Richards Engineering, Inc., Eugene
    Project Planner: Dorene Steggell, (541) 346-5606

    This project addressed the siting and installation of a large, donated sculpture titled Akbar's Garden by prominent Northwest artist Lee Kelly. The Straub Hall Quadrangle was selected by the artist and the donor as an appropriate site for the sculpture, which was installed there in June 2002.


    (WILLIAM W.) KNIGHT LAW CENTER

    Exterior NW photo , Exterior West , Interior 1, Interior 2, Interior 3
    Link to Law Center's Blueprint tour and Factsheets

    Size: 138,000 SF new construction (4 floors)
    Total Project Budget: November 1996 emergency board $24.5 million ($10.3 million F-bonds, $13.7 million gifts, $500,000 other resources) (Direct construction $21,689,575) (Project cost $24,400,632)
    Architect: Yost Grube Hall, Portland
    Construction Firm: Hoffman Construction Co., Portland
    Project Planner: Chris Ramey
    Project Manager: Janet Lobue

    The new Knight Law Center at the corner of 15th Avenue and Agate Street was the first stage of the Campus Development Project. The Law Center houses the Law library and has boosted overall Law School space by almost 50% to accommodate 565 instruction stations, 41 faculty offices, and several administrative areas. The new center better fits the way law is taught today, with more small classrooms and seminar rooms, a student lounge, a moot courtroom, areas for groups to meet, and access to the latest technology. It was designed by Portland architectural firm Yost Grube Hall. The Law School moved in Summer 1999 when final construction was completed.


    KNIGHT LIBRARY ADDITIONS AND ALTERATIONS

    Size: approximately 378,000 sf
    Total Project Budget: 1987 legislature for planning $780,000; $16.7 million in General Fund; 1989 legislature SB 5572 $9.9 million gifts, grants. (Phase I Direct construction $13,071,727) (Phase I Project cost $16,683,755) (Phase II Direct construction $8,644,103) (Phase II Project cost $10,894,019) Total project cost $27.4 million
    Architect: TBG Architects, Eugene, with Shepley Bulfinch Richardson and Abbott, Boston
    Contractor: Phase I construction: L.D. Mattson, Inc., Salem; Phase II renovations: S.D. Deacon Corp., Portland.

    Description: Phase I, a four-story addition of 138,000 gsf on the south side of the library and a small addtion on the Kincaid Street side added about 138,000 square feet to the library, more than doubling the seating capacity and increasing shelving space by about 27 percent. It transformed the interior so that the library services were fully modernized and make all parts of the building accessible. 240,000 sf in the existing building were renovated. Phase I was completed in fall 1992. Phase II was completed in mid-1994. Rededication was on October 14, 1994.


    LILLIS HALL/ GILBERT HALL ADDITIONS AND ALTERATIONS, PHASE THREE OF CAMPUS DEVELOPMENT PROJECT

    Size: net additional square footage is approximately 90,000 sf (four floors) plus replacement of 45,000 gsf (1952 Gilbert bridge) and remodeling of 37,000 gsf (east and west buildings, three floors).
    Total Project Budget: Lillis Hall: 1997 legislature SB 5536 $3.45 million G-bonds, $100,000 F-bonds, $3.45 million gifts plus 2001 legislature SB 5525 $33 million gifts. (Project cost $37.3 million)
    Gilbert Hall Additions and Alterations: 1993 legislature SB 5503 $7.5 million gifts; 1997 legislature SB 5536 $3,450,000 G-bonds, $100,000 F-bonds; $3,450,000 gifts.
    Architect: SRG Partnership, Portland, OR (contact: Hussain Mirza), (503) 222-1917
    Construction Firm: Lease Crutcher Lewis, Portland, OR (CM/GC), (503) 223-0500
    Project Planner: Fred Tepfer, (541) 346-5564
    Project Manager: Janet Lobue, (541) 346-5259

    The Lillis Hall/Gilbert Hall Additions and Alterations Project represents the final stage of the Campus Development Project. It relieved some of the need for general classroom space on campus.

    The newly configured Lillis Business Complex, which houses the Lundquist College of Business in four separate, linked structures, connects the UO's west entrance to the Memorial Quadrangle. Its prominent location and Gilbert Hall's historic role as the first element of what became the Memorial Quadrangle (listed on the National Register of Historic Places) give it pivotal importance both on the campus map and in campus history.

    This project is the first comprehensive addition and alteration project for Gilbert Hall in nearly 50 years. Since the center bridge connector (commonly referred to as the "Commonwealth Bridge") was opened in 1952, this building complex has been expanded and remodeled, but always without a comprehensive study of the long-range needs of the College of Business.

    The project created a unified facility that fosters interaction among students and faculty and supports teaching and learning in the classroom, in self-directed teams, and in internships. It gives the College state-of-the-art teaching and support facilities, a new look and a new front door onto the campus that it and the rest of the university can be proud of.

    Structural - Degenkolb Engineers; Mechanical/Electrical/Civil - Balzhiser & Hubbard Engineers; Landscape Architect - Cameron, McCarthy, Gilbert & Scheibe; Life Safety Ð Creighton Engineering.

    Status: Construction of Lillis Hall was completed in late fall 2003. Planning began in 2004 for renovation of the historic Gilbert (east) and Peterson (west) wings.


    LIVING LEARNING CENTER

    Size: approximately 120,000 gsf (two buildings)
    Total Project Budget: 2003 legislature HB 5028 $27 million auxiliaries (Housing)
    Architect: Zimmer Gunsul Frasca Partnership, Portland
    Contractor: John Hyland Construction, Inc.

    Description: Site work for this $27 million project began in August 2004. The project constructed about 400 beds of student resident-hall housing, instructional space, associated lounges and support space, and a dining facility. The project is located just north of 15th Avenue between Earl Hall and Walton Hall Complex on the site of the former outdoor tennis courts, which were relocated to a site near the Student Tennis CEnter. Construction on the two buildings, with a total gsf of approximately 120,000, began in winter term 2005. The buildings were ready for occupancy fall term 2006.


    MANY NATIONS LONGHOUSE

    Longhouse web site

    Size: 3,500 square feet new construction (one story)
    Total Project Budget: 1991 legislature $545,000 gifts (authorization expired); 1995 legislature SB 5555 $650,000 gifts; $350,000 student building fees; $810,000 gifts (Direct construction $726,000) (Project cost $1,116,986)
    Architect: Jones & Jones Architects and Landscape Architects, Seattle, WA, (206) 624-5702
    Construction Firm: Preferred Construction Inc., Springfield, OR (541) 726-8990
    Project Planner: Chris Ramey, (541) 346-5562
    Project Manager: George Bleekman, (541) 346-2625

    A conceptual design by Jones & Jones Architects for a new Native American Longhouse was completed in Spring 1998. As described in the conceptual design, the longhouse "will express the essential cultural values of welcome, community, and learning for Native American students and peoples. The building will serve as a gathering place... where Native Americans and non-natives can interact and learn from each other."

    The new longhouse is located on the site of the former longhouse. The all-wood building has a Great Room for large gatherings, modeled after traditional longhouses of the Kalapuya Indians. Other features include an office, a kitchen, and space for outdoor events.

    Status: Completed in January 2005. Grand opening held January 11, 2005.

     


    MCARTHUR COURT IMPROVEMENTS

    Total Project Budget: Athletic department revenue and Capital Repair funds. (Direct construction (roof) $199,110, (seating) $367,160) (Project cost $630,729)
    Architect: Architects Four, LLC, Salem.
    Contractor: (Roof replacement): 2G Construction, Inc., Eugene; (Seating modifications): Nor-Pac Systems, Inc., Kent, WA.

    Description: Two 1996 projects totaling $1.7 million replaced the 70-year-old lamella roof with structural steel trusses and completed improvements to the interior of Mac Court, including new flooring, ceilings, lighting, cabinetry, display cases, and painting of existing surfaces. An additional $600,000 project, seating modifications, was completed in May 1997. The project, replaced existing bleacher seating on the main level of Mac Court. Project completed 1996-1997.


    MCKENZIE HALL RENOVATION

    Exterior, Interior Photo, Corridor Photo

    Size: approximately 80,000 SF renovation (4 floors)
    Total Project Budget: 1997 legislature SB 5536 $4.5 million ($2.25 million G-bonds, $2.25 million building use credits and private gifts) (Direct construction $3.2 million, Project cost $4.1 million)
    Architect: SRG Partnership, Portland (Contact: Hussain Mirza)
    Construction Firm: Wildish Building, Eugene
    Project Planner: Fred Tepfer
    Project Manager: Janet Lobue

    The second stage of the Campus Development Project was the renovation of the former Law School building for university classroom and office use by the College of Arts and Sciences and other departments, including public interface components of University Computing.

    The renovation of McKenzie Hall (formerly called Grayson Hall) included the creation of new, state-of-the-art classrooms and offices in former library space, improvements to existing classrooms, creation of computer labs and seminar rooms, and other interior remodeling. It also included improvements to accessibility, entrances, approaches, and the existing courtyard.

    The first floor continues to provide space for existing classrooms; University Computing maintains a documents room and a general university computer lab. Its software consultants, Help Desk, and computer repair programs are also housed on this floor. Existing classrooms and lecture halls on the first floor have been enhanced to support a wider range of teaching styles and methods.

    Two of the building entrances have been modified to provide an improved connection with the university, orienting the building toward the rest of campus. The university contracted separately with Cameron McCarthy Gilbert & Scheibe, landscape architects, to design these improvements.

    The second floor was remodeled for the department offices of History and Ethnic Studies. The original moot court has become a film studies classroom; the law library space has been converted to new flexible media-equipped classrooms, and the original lecture halls have been improved with better lighting, enhanced acoustics, and provisions for multimedia presentation.

    The third floor has remained faculty offices and includes a faculty lounge, seminar rooms, GTF offices, a GTF lounge and a classroom. Open spaces have been made into shared commons.

    Three new seminar rooms, a multi-use classroom, and the Social Sciences Instructional Laboratory were built on the fourth floor, as well as space for the Oregon Survey Research Laboratory.

    Construction was completed in summer 2000 and the building was occupied the beginning of Fall term.

     


    (ED) MOSHOFSKY SPORTS CENTER (INTERCOLLEGIATE ATHLETIC FACILITIES IMPROVEMENTS PHASE 1) (including the Ed Moshofsky Indoor Practice Facility)

    Exterior photo, Interior 1, Interior 2, Interior 3

    Size: 106,845 SF new construction (1 floor)
    Total Project Budget: September 1996 emergency board $13.8 million- gifts (Direct construction $11.9 million) (Project cost $13,999,426)
    Architect: WBGS Architecture, Eugene
    Landscape Architect: Cameron McCarthy Gilbert & Scheibe
    Construction Firm: Chambers Construction, Eugene
    Project Planner: Chris Ramey
    Project Manager: Garry Fritz

    This project consists of an indoor practice facility which opened in Fall 1998, a soccer field, and other practice fields for intercollegiate athletics near Autzen Stadium. It provides the university with indoor practice areas for women's softball, women's soccer, men's and women's track and golf, and football, along with outdoor natural grass practice and competition facilities for women's soccer and outdoor practice facilities for all teams.


    (ED) MOSHOFSKY SPORTS CENTER (INTERCOLLEGIATE ATHLETIC FACILITIES PHASE 2)

    Exterior, Interior, Duck Shop

    Size: approximately 22,600 SF in additions (1 & 2 floors)
    Total Project Budget: 1999 legislature SB 5021 $2.8 million gifts (Direct construction $1.99 million) (Project cost $2.6 million)
    Architect: WBGS Architecture, Eugene
    Construction Firm: Chambers Construction, Eugene
    Project Planner: Chris Ramey
    Project Manager: Charlene Lindsay

    Phase II consisted of two additions to the Phase I indoor sports practice facility adjacent to Autzen Stadium (1998). These additions were part of the original building design and were planned as eventual enhancements. The two additions contain team medical training and meeting rooms, classrooms, a commissary, a letterman's lounge, and storage for pre-game functions.

    Construction was completed summer 2000.


    (JORDAN SCHNITZER) MUSEUM OF ART ADDITIONS AND ALTERATIONS

    Museum of Art web site

    Size: approximately 38,000 sf addition and 25,000 gsf renovation (three floors)
    Total Project Budget: 1999 legislature SB 5021 $12,720,000 ($6,360,000 G-bonds, $6,360,000 gifts) (Direct construction $10,436,061) (Project cost $12,719,948)
    Architect: SRG Architects, Portland, OR (contact: Dennis Cusack), (503) 222-1917 with design consultants Hammond, Beeby, Rupert, and Ainge, Chicago
    Construction Firm: Wildish Building Company, Eugene, OR, (541) 485-1700
    Project Planner: Chris Ramey, (541) 346-5562
    Project Manager: Alex Gordon, (541) 346-5219

    Built in 1932, the Museum of Art is Oregon's premier academic art museum. It receives between 40,000 and 50,000 visitors annually, many arriving from off campus. The Museum of Art's audiences, collections, programs, and staffing have long since outgrown the facility. This project provided an addition for new galleries, collections storage, a loading dock, new offices, and an auditorium. It renovated existing spaces including development of a climate control system, new electrical systems, asbestos abatement, and ADA improvements. The creation of an outdoor sculpture courtyard was also part of this project.

    Listed on the National Register of Historic Places, the building itself is considered to be an important part of the Museum's collection of artwork. The project gave careful and sensitive consideration to the building's campus location, its unique architectural design, and its historic setting.

    Status: Construction began in fall 2002 and was completed in January 2005. The official reopening was January 23, 2005.


    MUSEUM OF NATURAL AND CULTURAL HISTORY EXHIBIT DESIGN

    Total Project Budget: 1997 legislature SB 5536 $1.46 million gifts (Project cost $900,400)
    Architect: WOW Arts and Exhibits, North Bend, OR
    Contractor: Presentation Design Group, LLC, Eugene

    Description: Following the creation of a new interpretive master plan for the museum's exhibits and the creation of a conceptual design, the museum constructed new exhibits, which reopened in winter 2005. The main exhibit hall was completely revamped to dramatically showcase a new exhibit that celebrates the past 15,000 years of Oregon's cultural history. The new exhibit, "Oregon- Where Past is Present", was nearly a year in the making and offers a fascinating walk through space and time, telling Oregon's dynamic story. The new display showcases the state's four geographical regions: the Great Basin, the Columbia Plateau, the Coast, and the Interior Valleys. Visitors learn about each region through recreated environments, artifacts, interactive exhibits, photographs, graphics, and text. In the center of the exhibition hall is a recreated "laboratory" with a variety of interactive opportunities to help individuals explore the science behind the stories. Completed Feb. 11, 2005.


    MUSEUM OF NATURAL AND CULTURAL HISTORY NORTH ADDITION

    Size: 1,600 gsf
    Total Project Budget: 1991 legislature SB 5520 $1,570,000 gifts; 1997 legislature SB 5536 $1,460,000 (authorization transferred to Museum of Natural and Cultural History Exhibit Design project (see above); north addition required no authorization since it was below $500,000. (Direct construction $202,171) (Project cost $250,000)
    Architect: L.A. Kersh Architecture, Eugene
    Contractor: Morris P. Kielty, General Contractor, Eugene

    Description: This modest 1,600 gsf addition to the museum was anticipated when the building was constructed in 1987. Funded from private gifts, it contains a conference room, private offices, a research office, men's and women's toilets, an accessions work area with adjacent records room, and a receiving area. The addition allowed the current research/accessions/records area to be reused as offices for museum staff. Project was completed in August 1997.


    OIMB (LOYD AND DOROTHY) RIPPEY LIBRARY

    Total Project Budget: 1998 emergency board; $600,000 private donation, $40,000 from UO Research VP for relocations. (Direct construction $503,546) (Project Cost $618,925)
    Architect: Church & Merrill Architect, Portland
    Contractor: Joe Brown Construction, North Bend

    Description: The expansion of the OIMB library began in December 1996 with discussions with a private donor. Planning Office staff provided OIMB with revised example building schemes and revised cost estimates. Project completed in 1999.


    OIMB TERWILLIGER LAB REMODEL

    Oregon Institute of Marine Biology web site

    Size: remodel Cfloor)
    Total Project Budget: June 1998 emergency board $625,000 (combination of state funds and a National Oceanography and Atmospheric Administration (NOAA) grant) (Direct construction $503,038) (Project cost $594,900)
    Architect: Crow/Clay Architects, Charleston, OR, (541) 269-9388
    Construction Firm: Joe Brown Construction, North Bend
    Project Planner: Fred Tepfer, (541) 346-5564
    Project Manager: Alex Gordon, (541) 346-5219

    Description: This project provided additional office and lab space on the second floor of the Oregon Institute of Marine Biology's Terwilliger Building. Phase 1 of the project included an addition to the second floor. The exterior shell of this addition was completed Summer 2001. Phase 2 of the project included remodeling the unfinished attic space on the second floor, primarily as a lab and office suite for OIMB's director. Phase 2 was completed December 2002.


    POWELL PLAZA (HAYWARD FIELD)

    Click here for Rendering of Powell Plaza

    Click here for Rendering of Powell Plaza Entry

    Location: Corner of Agate and 15th Streets
    Total Project Budget: $950,000 (Project cost $1,225,000)
    Landscape Architect: Cameron McCarthy Gilbert Scheibe (541) 485-7385
    Construction Firm: Brown Construction Company
    Project Planner: Chris Ramey (541) 346-5562
    Project Manager: Charlene Lindsay (541) 346-5276

    The Hayward Plaza Project brings together two long-standing needs at this facility: creating a welcoming "front door" for the facility and providing an opportunity to recognize the great heritage of Hayward Field and the University of Oregon Track and Field programs.

    This project creates a welcoming arrival point for Hayward Field as well as enhancing a significant campus entrance. The plaza project incorporates displays telling the story of Hayward Field and our Track & Field programs. The design provides for access to these display areas for casual, weekday visitors as well as those attending events at the facility.

    Status: Completed 2005.


    RESIDENTIAL AREA CONCEPTUAL STUDY

    For more information, contact the University Planning Office:

    Chris Ramey - Director and Architect (541) 346-5562
    Christine Thompson - Planning Associate (541) 346-5572


    SCIENCE FACILITIES ADDITIONS AND ALTERATIONS COMPLEX

    Total Project Budget: $45 million in federal grant (NOAA) and state funds.
    -Willamette (Sci V)-$18,232,600 (1989) (Wildish Construction)
    -Deschutes (Sci IV A)-$3,667,660 (1990) (Doug Hyland)
    -Streisinger (Sci IV B)-$9,341,800 (1990) (Wildish Construction)
    -Cascade (Sci VI)- $8,526,500 (1991) (Robinson)
    -Museum of Natural History relocation-$769,100 (1987) (McKenzie Commercial)
    -Millrace 1 and 2 (relocations of AAA studios)-$601,400 (1986) (McKenzie Commercial)
    -Pacific Hall remodel for AAA- $500,000 (1991) (McKenzie Commercial)
    Architect: for all four science buildings- Ratciff Architects, Berkeley
    Contractors: see above.

    Description: This project included the construction of a complex of four major science buildings, the construction of a new Museum of Natural History and two smaller architecture studio buildings to replace dislocated facilities, and a remodel of a former science building for Architecture and Allied Arts, which lost about 15,000 net square feet of programmatic space to construction of the new science buildings. Project completed from 1989-1991.


    SHIRE RETREAT AND STUDY CENTER AT THE JOHN YEON PRESERVE FOR LANDSCAPE STUDIES. FEASIBILITY AND SITING STUDY.

    Project Planner: Dorene Steggell (541) 346-5606
    Landscape Architect: Walker Macy (503) 228-3122

    The Shire occupies 75 acres along the northern bank of the Columbia River Gorge directly across from Multnomah Falls, approximately 35 miles east of Portland. It is a carefully designed landscape in a natural context with a sculpted lawn, a series of meadows, vista points, river bays, and walking paths created by John Yeon over a 30-year period. The School of Architecture and Allied Arts plans to create a retreat and study center on the site.

    The Shire, with its Retreat and Study Center, will become a national and regional center for Pacific Northwest landscape and planning studies while being preserved as an example of landscape design. A study examining the feasibility and siting options for the development of the Center was completed in January 2005.

    See the following website for more information regarding The Shire.
    http://landarch.uoregon.edu/index.cfm?mode=facilities&page=shire


    SOUTHGATE ENTRANCE

    Photo 1, Photo 2

    Total Project Budget: Project cost $50,338
    Construction Firm: 2G Construction, Eugene
    Landscape Architect: Cameron McCarthy Gilbert & Scheibe, Eugene
    Project Planner: Dorene Steggell

    The signage improvements project at the Southgate entrance is the last of three priority entrance signage projects proposed by a review of campus signage several years ago. The other two locations are Westgate, where signs were installed last fall, and the corner of Franklin Boulevard and Agate Street, where a large "University of Oregon" sign was installed in the spring of 1998.

    Southgate improvements augment other University Street improvements made in recent years and serve as both a welcome gateway and means of orientation. The design contains elements of the existing Westgate (13th and Kincaid) with differences in materials to reflect the immediate context. The Southgate design replaced the previous light standards with taller, more massive lighting elements similar in style to the Westgate design. A bronze, interlocking block 'UO' is embedded in brick pavement across the entrance.

    Construction was completed in Summer 1999.


    SOUTHGATE IMPROVEMENTS

    Total Project Budget: (Direct construction $103,147) (Project cost $57,897)
    Architect: Cameron McCarthy Gilbert, Eugene
    Contractor: 2G Construction, Eugene

    Description: New curbing, paving units, irrigation, planting and lighting were installed on University Street between 15th and 18th Avenues. Project completed in 1994.


    SPENCER VIEW FAMILY HOUSING

    Total Project Budget: Auxiliaries (housing); 1989 legislature SB 5572 $10 million F-bonds; 1993 legislature SB 5503 $9 million F-bonds; 1995 legislature SB 5555 $6 million F-bonds. (Direct construction $12,777,356) (Project cost $13,772,551) Amazon demolition and site work: (Direct construction $958,681) (Project cost $1,085,468)
    Architect: gLAs Architectural Group, Eugene
    Contractor: John Hyland Construction Inc., Springfield

    Description: A $13.8 million project consisting of 264 units of two- and three- bedroom apartments, has been constructed on the site of the dilapidated Amazon Family Housing Complex, which was demolished in 1995. Phase I, consisting of 132 apartments and a community center building was completed for fall 1996. Phase II consisted of an additional 132 apartments ready for occupancy in 1997.


    STUDENT RECREATION [AND FITNESS] CENTER, Phase I - Esslinger Hall Additions & Alterations

    Exterior north, Exterior east, All-year field

    Implementing The Oregon Experiment with the Recreation Center project

    Size: approximately 79,000 SF remodeled/renovated; 49,000 SF addition ( 1 & 2 floors)
    Total Project Budget: 1997 legistlature SB 5536 $18,140,000: $16,640,000 F-bonds (student building fees & student incidental fees) $1.5 million gifts (Direct Construction $16,657,016) (Project cost $19,195,830)
    Architect: TBG Architects & Planners, Eugene, with Cannon Parkin, Los Angeles
    Construction Firm: Hyland Construction, Eugene
    Project Planner: Chris Ramey
    Project Manager: Mark Henry

    This project consisted of the renovation and expansion of Esslinger Hall and playing fields. The first phase included an addition which houses new strength and fitness areas, a three-court gym with a running track, a rock-climbing wall and a juice bar. The existing locker rooms and laundry areas were remodeled for locker rooms, administrative offices, the Slocum Lab, athletic training areas, and storage areas. The first phase also included an exterior, lighted, artificial field. Other improvements included new accessibility ramps and other minor repairs. Construction began in March 1998 and was completed in Fall 1999.

    The second phase of construction included renovation of the existing gyms, courts and multipurpose rooms as well as the extension the grass field by the Autzen footbridge. Construction was completed in Spring 2000.


    STUDENT RECREATION [AND FITNESS] CENTER, Phase II- Student Tennis Center

    Exterior Photo

    Size: six new courts plus approximately 3,000 SF for the viewing area (Phase I, 1 floor)
    Total Project Budget: approximately $3.6 million (1999 legislature SB 5021 $1,515,80-0 F-bonds, $2.12 million Intercollegiate Athletics & student fees) (Project cost $2,046,461)
    Architect: TBG Architects, Eugene
    Construction Firm: Hyland Construction, Springfield
    Project Planner: Chris Ramey
    Project Manager: Mark Henry

    During the planning phase for the Recreation and Fitness Center, discussions were held among the project user group, representatives of Intercollegiate Athletics, and PARS staff about how to combine funding for the Recreation Center project with Athletic Department funding in order to build a new enclosed tennis facility.

    The fully enclosed facility for instruction, recreation, and intercollegiate tennis users replaces four covered courts that were demolished to make way for the Rec Center. The tennis facility includes a small office and storage area to be shared by all of the facility's users; restrooms; and a viewing area for observing matches or instruction. It consists of a prefabricated metal-roofed structure enclosed with 18-foot walls of articulated concrete masonry units.

    The Student Indoor Tennis Center was built in phases. Phase I, completed in Fall 2000, consisted of a six-court building with associated spaces and a central viewing area. A later phase expanded the building from six to eight courts and added a raised viewing platform.


    STUDENT RECREATION AND FITNESS CENTER CONCEPT STUDY

    PARS worked with the Planning Office and Yost Grube Hall Architects of Portland to analyze the facility's needs and develop a conceptual plan for future additions and alterations. The study was completed spring 2004. It describes two phases of expansion with a total of 111,000 square feet of new construction and 31,700 square feet of renovation. It includes conceptual floor plans, models, and rendered elevations, integrating the existing facility with the new.

     


    SUSTAINABLE DEVELOPMENT PLAN

    Sustainable Development Plan

    Project Planner: Christine Thompson

    The university has prepared guidelines for campus sustainable development that have been adopted as part of the Long Range Campus Development Plan. The Campus Planning Committee believes that the University of Oregon should be a world leader in creating and maintaining an environmentally sustainable institution. The University should set examples in the design, construction, and operation of the campus, the management of its fiscal and human resources and the actions of its faculty, staff, and students.

    The Sustainable Development Plan was prepared by the Development, Policy, Implementation, and Transportation (DPIT) Subcommittee of the Campus Planning Committee as directed by the university president. It was reviewed and approved by the Campus Planning Committee at a public hearing October 5, 2000. The plan became effective February 15, 2001 when the University received notice that the City of Eugene had determined the "sustainable development" pattern to be consistent with the Area Metro Plan.

    Click here for additional information and to view a copy of the Plan.


    TENNIS COURTS RELOCATION/UPGRADES TO PARS FIELD AND 400-METER TRACK

    Total Project Budget: $1.8 million (2005 legislature SB 5514 $850,000 F-bonds; $950,000 other)
    Architect: Cameron McCarthy Gilbert & Scheibe Landscape Architects

    Description: Relocation of the tennis courts displaced by the Living Learning Center project was the catalyst of a more ambitious project to improve the area of the Intramural Field along 18th Avenue and the adjacent Hayward Field practice track. The improvements included six tennis courts, two sand-based grass playing fields for soccer, football, and other sports, and a 400-meter warm up/jogging track. Construction began in July 2005. The tennis courts were completed fall term 2005, and the grass fields in spring 2006.


    UNIVERSITY HEALTH AND COUNSELING CENTER ADDITIONS AND ALTERATIONS

    Size: approximately 39,000 sf remodeled, 11,000 new sf
    Total Project Budget: 2003 legislature HB 5028 $10,080,000 student building fees.
    Architect: BOORA Architects
    Contractor: Fortis Construction, Inc., Lake Oswego

    Description: This $10 million project conssited of the renovation of almost all of the Health and Counseling Center's existing spaces (39,000) and the addition of approximately 11,000 new square feet. The completed project unified the building into a coherent student-focused facility to provide primary care outpatient services, health education, and counseling and testing services. The design created a two-story addition on the northeast corner of the site (along 13th Avenue) and a one-story extension of the existing southeast wing. New internal courtyards were created by linking each of the three eastern building wings with two corridors on the east side of the buildings. The lower level includes a refrence library, the building hearth, meeting rooms, and a lactation room. The main floor includes medical clinics and associated functions, and the second floor houses the Counseling and Testing Center, physical therapy, and administrative functions. Construction began in September 2005 and was completed in November 2006.


    UNIVERSITY STREET AXIS FRAMEWORK STUDY

    University Street Concept

    Size: exterior
    Total Project Budget: approximately $52,750
    Landscape Architect: Moore Iacofano Goltsman, Inc., Eugene
    Project Planner: Dorene Steggell

    The goal of this study was to develop a new vision for University Street and common open spaces that intersect the heart of the campus. A User Group, Focus Group, and campus-wide comment session offered opportunities for the campus community to participate.

    The study was completed in Spring 2001.


    VIVIAN OLUM CHILD DEVELOPMENT CENTER

    Construction Photo 1, Construction Photo 2

    Size approximately 2,600 SF addition (one story)
    Total Project Budget: 1993 legislature SB 5503 $1.24 million F-bonds, 1999 legislature SB 5021 $625,400 ($339,200 F-bonds, $286,200 gifts) (Direct construction $412,127) (Project cost $541,584)
    Architect: De Norval Unthank Architect, Eugene (Phase I); Poticha Architects (Phase II)
    Construction Firm: John Hyland Construction Inc, Springfield; Morris P. Kielty General contractor, Eugene
    Project Planner: Dorene Steggell
    Project Manager: Janet Lobue

    The existing Vivian Olum Child Development Center was designed to be developed in two phases. The architect for the original design, De Norval Unthank, worked with the user group to design Phase II, an addition (the Lois Schafpf Reed Wing) to the existing center. The addition allows the center to consolidate its program into one building, and to provide services to 13 additional children and their families. The program and size are similar to the originally planned Phase II. The configuration on the site was slightly modified to allow for more contiguous space to be left to the north of the building. Site preparation work began in Fall 2000 with demolition of one of the old, existing structures along the alley to the west of the existing center.

    The schematic design phase was completed in Summer 1999. Construction was completed in Fall 2000.


    ZEBRAFISH STOCK CENTER

    Size: 12,350 gsf
    Total Project Budget: September 1997 emergency board $1,500,000 F-bonds (BUC); January 1999 emergency board $1,800,000 ($1 million grants and $800,000 BUC) total project $3.3 million. (Direct construction $2,825,253) (Project cost $3,369,415).
    Architect: Gerald McDonnell & Associates, Eugene
    Contractor: John Hyland Construction, Eugene

    Description: This 12,350 gross square feet structure is located on an approximately half-acre site in the Riverfront Research Park, directly north of the University of Oregon's main campus. The facility, which houses the Zebrafish International Resource Center, is a leading resource for breeding zebrafish for use in world-wide research and serves as a central repository for genetic research using the organism. Project was completed in 2000.


    15TH AVENUE IMPROVEMENTS

    Total Project Budget: (Direct construction $233,575)
    Architect: Cameron McCarthy Gilbert & Scheibe Landscape Architects
    Contractor: Babb Construction/ Delta Sand & Gravel & Construction Co., Eugene
    Project Planner: Fred Tepfer

    The 15th Avenue improvements, built in the summer of 2004, increased parking significantly in the area of the Living Learning Center and also enhanced that part of campus with new trees, shrubs, irrigation, raised pedestrian crossings, and other features.


    18TH & AGATE STUDENT HOUSING

    Total Project Budget: (Direct construction $886,100) (Project cost $1,414,805)
    Architect: Center for Environmental Structure, Berkeley (Christopher Alexander) and Thallon and Edrington, Eugene, joint venture.
    Contractor: 2G Construction, Inc.

    Description: Twenty student apartments in a complex of four buildings and a small laundry facility were constructed. To clear the site, one house was demolished, two were sold and moved of campus, and four were moved to East Campus Sites. Construction was completed in 1994.


    For additional information, contact Campus Planning and Real Estate at (541)346-5562