Baseball Park  
   
   
Current Status  

Baseball Park Conceptual Design Study completed

Phase I - Field Package: Early work packages underway; Construction Bid Packages out; Begin Construction by end of August

Phase II - Stadium Design: Program Verification and Schematic Design Phase underway

Construction Manager / General Contractor selection completed

 
Project Timeline  

Phase I - Field Package: Build Permit estimated to be issued August 28, 2008

Phase II - Stadium Package: Schematic Design Completion expected October 2, 2008; Design Development Dec 23, 2008; Construction Documents April 9, 2009 Early work package starts July 7, 2008

 
Project Summary  

Site: Northwest corner of the east side of Autzen Stadium

Size: TBD

Legislative Authorization: Jume 2008 Emergency Board Session

Expenditure Limitation: $20 million gifts

Total Project Budget: $15 to $18 million

Architect- Concept Design Study: Robertson Sherwood Architects, Eugene
                   Phase I, Field Package: Cameron McCarthy Gilbert Scheibe, Landscape Architects, Eugene
                   Phase II, Stadium: DLR Group, Portland

Construction Manager / General Contractor: Lease Crutcher Lewis, Portland

Project Planner: Gene Mowery, Campus Planning and Real Estate, 6-5593

 
Project Description  

Phase I - "Field Package": Phase I includes the baseball field, player development area, scoreboard, video board, fencing, lighting, associated infrastructure, and temporary grandstands, dugouts, press box, toilets, and concessions. This portion of the project will be ready for competitive baseball play by spring 2009.

Phase II - "Stadium Package": Phase II is a stadium designed to accomodate 3,000 to 4,000 fans, that will include a covered player development area, clubhouse, press box, donor suites, concessions, plaza and landscape build-out, and associated infrastructure.  Phase II construction is expected to be complete by spring 2010.

 