Current Status  
Project completed December 2012. Data Center basement project to be completed March 2013.
 
Project Timeline  

Grand opening: March 1, 2013
Completed: December 2012

 
Project Summary  

Location:  1020 University

Size: 23,011sf addition

Legislative Authorization:

Expenditure Limitation: $26,890,387

Allen Hall Funding: $7,500,000 G-Bonds, $7,500,000 gifts, $2,192,000 other
Data Center Funding: $9,698,387 other

Architect: TBG Architects & Planners / Yost Grube Hall Architecture

Construction Manager/General Contractor: Lease Crutcher Lewis, Portland

Project Planner: Martina Bill, Campus Planning and Real Estate, (541)346-5880

Construction Project Manager: Janet Lobue, Capital Construction, (541) 346-5259

 
Project Description  
The Allen Hall Expansion and Remodel Project included a 23,011 sf addition in three stories and a basement to the existing building to accommodate the expanding School of Journalism and Communication and created an overall sense of building cohesiveness among the 1922, 1954, and 2012 wings. The addition includes additional office space for full-time, adjunct faculty, and graduate teaching fellows and two new classrooms. The renovation included energy and seismic upgrades to the existing 1922 north wing and 1954 west building and created a "Digital Commons" - a new teaching, learning, and collaborative digital work area centered on evolving curricular needs of digital media productions.

Grand Opening celebration is March 1, 2013.
 
Links  

Allen Hall Transformation

User group's website : http://pages.uoregon.edu/moxoby/Allen/Allen.html

2008 Conceptual Study, SERA Architects - Volume 1, Volume 1 drawings, Volume 2

 