818 East 15th Avenue  
   
   
Current Status  
Construction Complete
 
Project Timeline  

November 1, 2007: Occupied

 
Project Summary  
Proposed site:  818 East 15th Avenue

Funding: University funds

Architect: Robertson / Sherwood Architects, Eugene

General Contractor: Chambers Construction, Eugene

Project Planner: Gene Mowery, Campus Planning and Real Estate, 346-5593

Project Manager: John Weatherly, Facilities Services, 346-5276

 
Project Description  
This design-build project involves a change of use from a former fraternity house into surge space for programs temporarily displaced by capital construction/ renovation projects.
 
   

 

 
 